7 issues (filtered)17 topics
HighRoads

State reimbursement delays on highway projects

The state is taking months to reimburse the county for bridge and road work already paid for, and none of the county's bridge projects are in construction right now. As costs climb into the millions, slow reimbursements could strain county cash flow.

1 mention (1 this month)Last discussed Oct 15, 2026
HighRoads

South Danby Road Culvert Deterioration

A Danby resident told the committee a metal culvert dating to the 1800s is collapsing under South Danby Road, has never been inspected by the county, blocks fish passage, and sits under a 55-mph road. She says the whole road's residents share the problem and invited legislators to visit. The committee took her letter under advisement and asked the Highway Director for a status report.

2 mentionsLast discussed Sep 17, 2026
HighRoads

Federal and State Transit Funding Package

The committee recommended over $16 million in federal and state grants for TCAT, Gadabout, and county mobility programs — new buses, operations, and rider services. Almost none of it comes from county taxpayers; the only direct county cost is $50,000.

2 mentionsLast discussed Jul 21, 2026
HighRoads

Caroline Depot Road Culvert Replacement

A failing culvert over a Six Mile Creek tributary will be replaced with 80% state funding. The county's $324,665 share can largely be covered by highway crews' in-kind work, and design starts now so construction can happen in summer 2027.

3 mentionsLast discussed Jul 21, 2026
HighRoads

TCAT Facility and Funding Future

Two resolutions fix problems the FTA flagged in its audit of the county's transit funding: a purchasing oversight manual for TCAT and a Disadvantaged Business Enterprise plan. Both are needed to keep federal transit dollars flowing.

3 mentionsLast discussed Jun 18, 2026
HighRoads

Hines Road Bridge Replacement

The 70-year-old, two-girder bridge in Enfield will be replaced in a $3.376 million project — 80% federal, 15% state, only 5% county. The bridge will also be widened to at least 14-foot lanes so plow trucks can pass safely; construction is targeted for 2028.

5 mentionsLast discussed Jun 16, 2026
HighRoads

ITCTC 2026-2027 Operating Budget

Tompkins Cortland Community College's $34.5 million budget keeps county funding flat at $3.18 million — a 0% increase — while tuition stays the same and adult enrollment surges under the state's free community college program. The county's share will be raised through taxation in fiscal year 2027.

2 mentionsLast discussed Jun 8, 2026